Language:CHINESESENGLISH

Home > News > Steel processing security measures to ensure the
CONTACT US
  • Address:Pingtang Industrial District, Shipeng Village, Shishan Town, Nanhai District, Foshan City,
  • Phone:0757-81002668/0757-63323396
  • Fax:0757-81196682
  • Contact:Ben Zheng/13826981293 Kerry Lu/13751224830
  • E-mail:sbs@sbsprefabhouse.com
  • URL:http://www.sbshouses.com

Steel processing security measures to ensure the

Time:[2014-11-22]  Hits:4598

(1) steel processing security measures
1) small and medium sized construction machinery should be set in accordance with the orientation of the processing plant construction plane making reasonable arrangements to meet the assembly line needs.
2) The device must be set open hand operation.
3) drilling and lathe and other transmission parts should be installed shields, set secure block, sub-feeder.
4) Manual grinder should use unidirectional switches must be installed no less than 180 degrees shield and workpiece firmly trailers, prohibited the use of non-round, there are cracks and the remaining portion is not sufficient to 25cm wheel.
5) lifting and lashing rope with a safety factor should be sufficient to strengthen the usual checks, where surface wear, corrosion, broken wires than standard, killing bent, broken stocks, oil core, exposed shall apply.
6) The hook should prevent decoupling devices.
7) crane drivers should strictly follow the rules, according to the construction specifications, according to safety tests, operations and strengthen the usual maintenance work, seriously implement the "clean, smooth, tight, corrosion," the maintenance system.
(2) Coating Safety Precautions
1) The safety measures are mainly construction needs paint: paint the construction site must have good ventilation, ventilation conditions, such as when painting a bad environment, you must install ventilation equipment.
2) due to careless operation, when the paint spilled on the skin, can be used sawdust plus soapy water; not the best petrol or strong solvents to clean, so as not to cause skin irritation.
3) the use of mechanical descaling tools (such as a wire brush, rasps, pneumatic or electric blasting tools) clean rust layer, in order to avoid contamination of the eyes or injured, to wear protective glasses, and wear a dust mask, to prevent respiratory tract infection.
4) When painting harmful paints, need to wear protective masks, goggles and other protective items enclosed.
5) When spraying flammable volatile type of paint larger, prohibited the use of fire, strict compliance with fire safety rules to avoid fire or cause an explosion.
Wire 6) construction sites, according to the provisions of proof grade installation; motor starting device and power distribution equipment, should be explosion-proof, and to prevent the mist splash on light bulbs.
7) are not allowed to dress paints, solvents or paint cans with leftover opening placement. Dip coating or solvent waste cotton rags and other objects, must be promptly removed; painting environment or ingredients rooms should be kept clean, and out unimpeded.
8) The operator painting and construction, such as feeling headaches, palpitations or nausea, should immediately leave the construction site, in a well-ventilated environment fresh change of environment, such as still feel unwell, you can speed to the hospital for treatment.
Copyright:佛山市胜邦钢结构有限公司 Foshan Shengbang Steel Structure Co., Ltd. Record Number:粤ICP备13078463号